Programme
·
Alric Taylor, Permanent Secretary, Ministry of
Communications & Works ·
Claude E. S. Hogan, GoM Airstrip Project
Manager/Forum Facilitator ·
Stephen Young (DFID-M) – Engineering & Safety
Support Details ·
Stephen O’Driscoll – Management Dynamics &
the Implementation Process ·
Dave Dolan – Drainage & Hydrological Issues ·
Michael Barnard – Communications Issues ·
Claude Hogan (GoM) – Socio-Economic Climate &
Dimensions ·
Bill Millington, Director, Halcrow Group |
PRAYER
Pastor Buffonge: Gracious Father and our
God, as we come before your presence again tonight, we always count it a
privilege that we can come boldly to your throne of Grace.
Father as we go in to this discussion tonight we ask for your guidance
for you said that in all our ways that we should acknowledge you God and you
would give direction. So
Father as we go in to this session tonight we ask God that you will give
direction in these decision-making in the name of Jesus.
We give you thanks and we give you praise.
Amen.
C. Hogan:
Thank you very much Pastor Buffonge.
Your Excellency; Permanent Secretary, Alric Taylor; Sir Howard, DFID
Head; Deputy Commissioner of Police; other distinguished ladies and gentlemen, a
very pleasant evening to you. And
please forgive me—honorable Speaker and his wife—sorry I did not see you
there for a moment, sir. May I
however continue?
Having regard for the length of discussion that we are supposed to have
tonight. We have a very tight
program. Everything about this
airport project seems to be on a tight schedule but we have five gentlemen,
including myself, and we’ll be prepared to go through this program with you
tonight.
But before we do that we wanted to be able to set the framework for these
discussions and I’m very honored to invite one of our project officers for
this project – We have two project officers responsible for this project.
They are DFID, the Department for International Development-Montserrat,
London-Montserrat and locally from the Government of Montserrat side—the other
project officer is Mr. Alric Taylor, the Permanent Secretary, Ministry of
Communications and Works.
Without any further ado, may I ask you to please help me to welcome the
Permanent Secretary to set the tone for the discussions?
Permanent Secretary. (Applause)
A. Taylor:
Thank you very much Mr. Chairman. Your
Excellency, the Governor; Honorable Speaker of the House; Sir Howard; members of
the Halcrow team; distinguished ladies and gentlemen, good evening.
The Ministry of Communications & Works in association with the
airport design consultants have organized this forum tonight as part of our
public information strategy to inform the public on the proposed airstrip at
Geralds and indeed to provide an opportunity for interaction on key issues and
concerns allied to the proposed facility.
The Government of Montserrat has already taken a decision to construct a
temporary airstrip at Geralds. Whatever
“temporary “is defined to mean, the provision of this facility is important
for several reasons among which are: economic
and investment opportunities and also for the social and financial gains which
could arise from this. In fact, it
is my view that this facility could be the engine for redevelopment of
Montserrat.
Despite the perceived limitations, as a people we need to look for the
opportunities for maximizing the use of this facility.
There have been several schools of thought, which posit that an airstrip
at Geralds is not safe and neither will it offer opportunities for expansion in
the future. Alternate sites have
been identified by interested parties but the view of the experts is that these
alternatives do not satisfy the requirements or they could cause considerable
disruption to wider sections of the public if they were to be implemented at
this time.
It is my understanding that contrary to the views that abound on
operational safety of an airstrip at Geralds there are other airports in the
region where conditions are worse than those at Geralds and the records reveal
few, if any, accidents. However,
this is not to underestimate the need to ensure that the operation of an
airstrip at Geralds is safe.
Closely allied to safety is the need for improved security as a result of
the September 11th events. Montserrat
needs a safe airstrip where persons who have decided to travel by air
transportation can feel safe and less anxious when they travel into and out of
Montserrat.
As I understand it, risks are part of an airport’s operations but more
often than not, these are seemingly linked with the decision-making capabilities
of the operators using the facility. However,
every effort must therefore be undertaken to ensure that the infrastructure is
not a contributory factor to increased risks.
Siting an airport at Geralds has other implications too: relocation, land issues, access to other areas, housing,
noise pollution, etc. and Government is mindful of these and a Steering Group
comprised of members from key government departments has been set up to deal
with these matters. I have no doubt
that the requisite actions would be taken.
Tonight’s event then is an important one that seeks to take this
project forward. And the pleasure
is mine to extend a very warm welcome to all of you who have taken time out to
be a part of this important exercise. I
wish to extend a very warm welcome to the Halcrow team.
Members of this team are not new to our shores in that they were
associated with the previous project to realign Bramble’s Airport.
Let this then be an interactive evening where we could discuss the issues
in an honest—indeed, we’re in the Church—frank and cordial manner.
Once again, welcome to all of you. (Applause)
C. Hogan:
Thank you very much, Permanent Secretary, Ministry of Communications
& Works, Mr. Alric Taylor. And
as you might have gathered over the past few months, the Ministry of
Communications and Works is the client Ministry for the proposed airport at
Geralds.
Ladies and gentlemen, I have spoken several times in respect of the
airport project as sort of the lead person as Project Manager for a number of
issues, some of which, the Permanent Secretary has raised.
We are indeed, I think somewhat fortunate in so far as we can tonight sit
here and give consideration to the future of our island and our own personal
development as it may or may not be enhanced by an airport at Geralds.
But what is very clear to me as the Project Manager is that we have but
two choices at the moment given the time and place and situation in which we
find ourselves. Those two choices
are: to have an airport or not to
have an airport.
And then we have other wishes. We
might wish to have an airport but we’d like to have the airport fashioned and
designed to meet the needs and aspirations which we have set for ourselves.
We had an airport and we had dreams of a Bramble expanded and extended
and reoriented to meet our economic and social demands and our demands to
have—our hopes to have more tourists, more investors, more businessmen.
Unfortunately, some of those hopes were dashed when in 1995 the events of
Soufrière
Hills Volcano were visited upon us. And
we have had to relocate to north Montserrat, then a sparse, barren hinterland
where very few people had dreams of retiring in glory and sunshine.
But today, this is the place; this is the time in which we find
ourselves, really – making this part of north Montserrat the most habitable.
And I’m encouraged because I find that even nature looks like it’s on
our side because I remember when I was young and coming to the north it used to
look really dry and I wondered about vegetation and the environmental impact and
what about the Silver Hills? Why
were they so barren? But you
realize since we came over here the whole place turned green.
(Laughter) Anybody
observed that? I observed the whole
place turned green so I’m very encouraged.
But back to the question of to have or not to have—In that context of
where we have come from and where we find ourselves—and it has been
established by researchers in political science, etc. that once you have
developed to a certain level it is rather impossible to reverse that impetus in
your mind. And your whole being,
your whole spirit is motivated to move from where you were to where you want it
to be. And we have gone through a
reverse cycle. Indeed sometimes I
wonder if we don’t need more than four psychologists.
I might need two for myself.
But the reality is how do you adjust to a situation where psychologically
you are motivated to go from where you are in your mind to a new reality where
you have benefactors who can say to you (legally so) that I am required to give
you so much resources to satisfy so much of your needs over so much of a period
of your time and really, at the end of the day, the choice is yours as to how
you make it? Whether you’re going
to creep before you walk or you’re going to start to walk before you even
creep because really that is the situation we find ourselves.
So how do we answer the question to have or not to have? It’s an impossible question to answer. So I think the Government of Montserrat has done the really
credible, bold thing of progressing on a path of attempting to resolve for the
people of Montserrat some form of an approach to a destiny which we have already
fixed in our minds.
So the struggle is to really define and design and come up with what
ultimately are our needs in this situation.
What is affordable in this situation?
And how can we take best advantage of those resources which have been
given to us in this situation? So
really we are becoming, I think, a more self-determined people. But it’s a tough challenge and we continue as a people to
knock on doors to seek assistance, to do as the Agriculture Department say, to
grow our own and get involved in import substitution as we try to make our own
lives while, of course, there are all of these other factors which we need to
take into consideration.
The Honorable Chief Minister of Montserrat—I think he—Dr. John
Osborne, that is—He said it in a simple way when we were in London the other
day. A people on welfare could only
get poor or poorer because welfare is a trap and the trap of welfare is that
when you get on it, you lose your inclination to want to work and you lose a lot
of your self-respect. And you lose
your desire to live as a man. And
this is the question of whether we want to wait upon the Lord or we’ll help
ourselves while the Lord helps us.
And this is the context in which I present to you tonight, the next stage
of the implementation of an airport project for Montserrat which offers us the
opportunity right now to be busy, to remain busy, to not lose sight of the fact
that we have to work to keep practicing to work, to keep your brain in tune with
the idea that you are in a situation and you have to keep working yourself out
of it and there are not going to be any miracles about getting out of the
situation in Montserrat, but work.
And right now I know how the international community system works.
I understand that when you engage them it is not very easy to disengage.
So we have to work through the process where the United Kingdom
Government and the European Union Government have acceded to our request to
finance what we call a temporary airport and I will not seek to define it at
this time. But it has its
limitations but it has its advantages.
So might I invite you now to recognize that the Government has taken a
decision to move forward with the implementation of an airport at Geralds?
And in that regard, we have contracted the Halcrow Group.
They are no strangers to Montserrat.
They have worked at the Bramble’s Airport.
They have a long history of being involved in airport construction—50
years of it I understand. They have
built airports in St. Vincent and the Grenadines, in Nevis.
They are currently working in Dominica, Melville Hall.
And they were the ones who were commissioned at the time—just before
’95 to extend and reorientate the Bramble Airport.
So in a way, we have a set of people on a team who are – who have been
involved not only in airport but they have regional and local experience.
I have every confidence in their expertise.
And tonight, they’ll take you through the final design stage of what is
proposed to be the Geralds Airport or Airstrip Complex.
And they’ll try to guide you along as to how they’ll be proceeding
taking into consideration wind and safety studies, turbulence, modeling—a
number of issues.
But I think I’ve spoken enough and I think you now have your thinking
caps on and listen with a keen ear.
Ladies and gentlemen, we have from the Department for International
Development-Montserrat Office, Mr. Stephen Young, an engineer assigned
specifically to the Montserrat project. And
Stephen will quite soon introduce himself so you can hear how his voice sounds
otherwise than on radio.
On my immediate left is Mr. Bill Millington.
He’s the Halcrow Project Director, team leader for the Montserrat
group. He has a long and
distinguished tour of duty in the Caribbean, as I said, including Dominica, St.
Lucia, Nevis, St. Vincent.
The Project Manager from the Halcrow side is Mr. Stephen O’Driscoll.
He’s also an engineer. He
possesses exceptional coordinating skills as far as I’m able to discern and he
has a depth of knowledge in air transportation issues, which is his area of
specialization.
Mr. Dave Dolan, the gentleman with the gray air in the nice light green
suit is the drainage and hydrological engineering specialist for the project.
His main job is to ensure that full account is taken of the drainage base
in the Geralds area in such a way that the strip is not compromised in the
immediate or medium term.
Michael Barnard is a – I call him the old veteran—man of great wisdom
in—I think it’s (indecipherable) airports and navaids and
communications so you’ll want to hear from him tonight.
That’s his business. He
specializes in equipping commercial airport control towers with the optimum
range of equipment to ensure safe and effective communications between the air
operators and traffic control. He
also provides expert guidance on the other communications systems which must be
present at any licensed airport.
Those are our panelists. But
to bring you to the heart of the matter, we are going to have a keynote,
PowerPoint presentation from Bill Millington.
But I just wanted you to get a feel of the team by having them introduce
themselves and say a little word. I’ll
start with Stephen.
S. O’Driscoll:
Thank you very much Claude for those introductions.
Good evening ladies and gentlemen. It’s a pleasure to be here on the
island with you this week. As
Claude said my name is Stephen O’Driscoll and I’ll be the Halcrow Project
Manager for the Geralds Airstrip Project. I
guess I’m effectively Claude’s equivalent on the consultant’s side.
And my responsibility will be for the overall delivery of the project and
to ensure that the key project objectives—the delivery of a safe and
affordable airstrip at Geralds is actually achieved.
Bill, I think, will talk in more detail about the programming issues but
the target delivery date for this project is December 2003, which, in effect,
condenses our consultancy commission into quite a short space of time.
So my role will be to make sure that all the various components of the
work are drawn together and the appropriate conclusions are drawn and taken
forward. I’ll pass you on to
David.
D. Dolan:
Good evening ladies and gentlemen. I’m
David Dolan. My responsibility will
be the drainage design of the airport and I too am pleased to be here.
I’m not sure that I can have much answers at the moment.
M. Barnard:
Good evening ladies and gentlemen. My
name is Michael Barnard. I am
supposedly the expert in communications, radio and telephonic navigation aids,
meteorological systems and also on airport ground lighting.
S. Young:
Yes. Good night ladies and
gentlemen, distinguished guests. My
name is Stephen Young from the DFID office here on Montserrat.
I’m pleased to be here tonight and to represent DFID here.
I think and I hope that by doing so I demonstrate DFID’s commitment and
support to the government of Montserrat in progressing this project, which we
believe is vital to the sustained recovery of the island.
The brief that we’ve given Halcrow is to design an airport in
accordance with international standards. Those
international standards, which are the regulators’ methodology to make sure
that any airport that we build is entirely safe in operation.
Also those regulations ensure that we will then be able to license
operators to come in and out of there providing the commercial links to the
island that we need to let us get away from the presently heavily subsidized
transport services and to move forward.
We will need that airport to be in place as quickly as possible.
We need it to be constructed in accordance with the available finance.
We need to ensure that environmental and social considerations are fully
addressed in the way that the project is conceived and then implemented.
My role really is to work with the Project Manager, the Honorable Hogan,
to ensure that the consultants are working in accordance with their brief, that
they are meeting those requirements we set for them and also to ensure that
there’s the timely release of the necessary funds to allow the project to go
forward. So I am very pleased to be
here tonight and as far as I can, I’ll be pleased to answer any questions as
we go through. Thank you.
C. Hogan:
Thank you very much Stephen. And
folks, I’m just to tell you that timely release of money is good.
We have some money from the DFID people already so we are front loaded
and ready to roll. And just to get you thinking and get Bill a little less
anxious, Bill will be presenting us with a PowerPoint presentation and he’ll
be basically discussing where we are and where we are going.
Bill Millington, May I ask you to please address the Montserrat public?
Please help me to welcome Bill. (Applause)
B. Millington: Thank
you. Good evening ladies and
gentlemen, distinguished guests. I thank Claude for alerting my audience to my state of
anxiety this evening. In fact,
those of you who joined a little late probably missed his reference to his
vision of northern Montserrat turning green over the last five years, which
reminded me that I felt that I turned a distinctly whiter shade of pale at being
informed that only two days into our first visit, we’d be making this public
presentation. So I think we deserve
some prizes for bravery.
But in fact we are very well prepared for this situation because over the
last—probably eight months, this process of selection of my company and its
team has been quite a rigorous one. It
was by no accident that we find ourselves here. And indeed I personally was here, as was mentioned, back in
’95 when I lead the team, which engineered the realignment of Bramble Airport
before, of course, the circumstances brought the early closure of that project.
The firm, in fact, is no stranger to the Caribbean or island airport
projects. The last few years,
we’ve completed the project at Nevis for the runway strengthening and
lengthening, which is obviously is extremely local and relevant.
We’ve—currently, we’re helping the Government of Dominica to
establish a sensible strategy for the development of its two-airport system and
to steer the Government away from concept of massive airports, which are
unaffordable and unwanted, towards a more sustainable and affordable
development.
But further away from these islands we are actually completing a project
on the island of (indecipherable) in the northwest islands of our own
British isles, which poses similar challenges to this project here in that it is
difficult to make a fully commercial case for projects—airport projects such
as this but there are other factors which determine the need for these projects.
And indeed that project is looking good and it will be a lifeline
to—not just the islanders—but the economy, the tourism on the island and the
west coast of Scotland.
But I’m reminded of a project where a different decision was made and
to the detriment of the community. And
that is on the island of St. Helena where some years ago we were asked to look
at the potential for the establishment of a airport on an island, which never
actually had an airstrip. And, in
fact, I think I’m right in saying—by whatever definition, it is one of the
most isolated communities on earth.
And to this day, the population is still struggling to and there is an
exodus and degradation of the economic base of the island simply because
accessibility to the island is so poor and that the bull was not taken by the
horns and a decision made to develop air services.
Still, let’s not draw too many comparisons because the situation here
on Montserrat is unique in many ways. And
perhaps rather than dwell too much on history, I’ll come more to the point,
which is to describe the process by which we propose to bring this quite
fast-track design and development process to a speedy conclusion.
In fact, when we look at the program actually there’s hardly time to
breathe. It’s an extremely
fast-track program. We’re here
today having only been commissioned, in fact, on the— in the first week of
January. So we on our team, who are
usually deployed in much less pleasant parts of the world, I must say, have
converged here to make a rapid start to the project.
And in fact last week our geo-technical engineer, Mike Palmer who some of
you probably met was here even before we’d dotted the “i”s and crossed the
“t”s on our own contract with DFID. So
we are ourselves extremely enthusiastic and willing to help Government of
Montserrat complete this project in what—by any stretch of the
imagination—would be a very ambitious program.
That isn’t to say though that there are some serious obligations upon a
design team to satisfy all of the statutory requirements necessary, especially
in an environment where, as was referred to, the spotlight actually of some of
the regulatory authorities will be on this project. The events that occurred in New York in September have meant
that there is additional, shall we say, attention being paid obviously to
security.
But as if that wasn’t sufficient enough reason, this year actually
probably will be—don’t quote me on this—but one of the first, if not the
first international airport to be built after those events.
So the authorities not just the Government of Montserrat themselves,
which has the ultimate responsibility but also other agencies such as the
International Civil Aviation Organization, the International Air Transport
Association, the Department of Civil Aviation in Antigua—they will all be
working doubly hard to make sure that there are no shocks and surprises when
these plans are put together, that they’re adoptable, that they’re fully
endorsable and safe from a security point of view.
And further more, there have been some other changes in the regulations,
international regulations. We are
very lucky in the world of airports in that we do enjoy a set of standard
international regulations throughout and across the world, which help our cause.
But there have been improvements in the regulations, sharpening of those
regulations, which now we’re having to bring into force on existing and new
projects—to some extent, makes our job easier because we are starting from
scratch. But we’ve had
discussions with the regulatory and licensing authorities to make sure they’re
prepared for new sets of regulations, which are even tougher than those which
exist.
And having traveled around the Caribbean, of course, I’ll not dwell on
this point, but you’re all aware of the situation at some of the other
airports, Canefield (I’m traveling to tomorrow actually) you know, we all hold
our breath and cross our fingers when we are coming into some of those airports.
And when we look at the situation there, there is room for dramatic
improvement in standards.
We feel that here at Geralds, we have the opportunity, having being given
actually a very good site to start from to get things right from the beginning
and to actually improve upon – significantly improve upon the standards for
even better airstrips in the region.
So I shall now describe the process, which is effectively a technical
process. I’ll be leading a team
of engineers, architects, environmentalists, planners in bringing this project
to a healthy conclusion in a fairly tight program. And if you’ll bear with me, I’ll—in fact, I’ll just
move over here—If I can grapple with the technology.
This is the bit where I sort of turn white actually.
That’s Stephen Young here whose knowledge of the engineering factors
and the operational factors through his involvement in the project over the last
year or two is obviously of enormous value to a project team which is really
starting on this project, technically at least, from scratch.
On my side, the Halcrow side, myself—I have 25 years of experience, 26
years of experience in this area of airport planning and design, more or less,
throughout the world.
Stephen O’Driscoll, our Project Manager who has some 15 years of
experience in this area, has learned his trade in Australia, has been involved
in the work we are undertaking in Dominica at the moment.
Roy Marsden who is visiting in three weeks time whose task it will be to
determine precisely and to pinpoint aspects of the operational layout,
operational aspects and layout of the airport including runway length, aircraft
operating procedures, air traffic control procedures, aerodrome classification,
and aspects relating to the regulatory process.
Mike Barnard whose job it will be to determine the air traffic control
and communications requirements for the project, the lighting, navigational
facilities, precision approach path indicators, other avionics systems as we
call them—all of the special systems that go with an international airport to
ensure safe operating procedures.
Dave Dolan, our drainage specialist.
The site itself is on a watershed. There
are some significant drainage issues to be dealt with on that site, not simply
from the point of view of moving water from the watershed to the east and west
when the construction of the strip is completed but also dealing with runoff and
erosion from the project embankments off of the runway apron system into the
drainage gullies. It’s an area of
engineering, which is quite significant.
Mike Palmer has been here last week.
We considered that the geological aspects of this project could be very
critical to its viability. Although
some investigatory work had been done earlier, work that we’ve done in ’95
at Bramble demonstrated that there was a possibility that large boulders could
exist not far beneath the surface of the site at Geralds, in fact, anywhere on
the island and that itself could create problems and raise costs and might push
the project beyond the limits of affordability.
Not only that, there is the question of how to deal with the compaction
of material in order to ensure a long lifespan of the project itself.
Early results from the trial pits undertaken last week are very
promising. And it looks as if
we’re not going to have too many serious problems from the geotechnical point
of view.
In three weeks time our environmentalist will be visiting the island.
The environmental and social issues have been stressed as being of
significant importance to this project. We
may only be talking about a handful of movements a day at the outset, but
nonetheless, this is a new international airport.
Those operations may in fact be quieter than current helicopter
operations but there is still a responsibility on the design team, the
Government of Montserrat to fully explain what the environmental impacts, in
terms of noise and other construction-related impacts actually are.
And last but not least, Ken Cassell, our local associate. Ken worked with us on the previous project at Bramble.
And Ken will be responsible for architectural aspects of the project once
it’s been determined what will happen to the terminal building, which was
built as a temporary structure for the helicopter operation and the air traffic
control tower.
Now the objectives: We
mustn’t lose sight of the fact, as I mentioned earlier, that this actually is
a full international airport, not just a new facility but a facility that must
comply with all of the standards and regulations laid down by the International
Civil Aviation Organization and that process of planning and designing an
airport to meet international standards is a complex one even for a relatively
small facility.
The objective of the project, of course, is to facilitate fixed-wing
operations of Dash, Twin-Otter types and similar.
During the construction, the helicopter operation would continue and in
fact special provision must be made in the planning of the works to ensure that
that operation can continue safely whilst the contractor is moving tens of
thousands of cubic meters of material and other major construction works.
The objective is, of course, that ultimately the project must be licensed
by the licensing authority, which is a responsibility delegated to the
Department of Civil Aviation. That
the DCA of course are members or shall we say are subscribers to ICAO—follow
ICAO regulations and that the standards that we will plan and design the airport
to will comply with ICAO standards in accordance with DCA licensing procedures.
Now, it is also imperative that the aircraft procedures which are
designed—and this is also part of the remit—are fully safe.
Now, that is a complex process that involves the determination of
aircraft procedures which provide operations in terrain, which in the vicinity
of Montserrat is rugged, that therefore clearances on aircraft approaches all
satisfy international requirements, that the utilization of the airport in terms
of crosswind components fully complies with international requirements and that,
therefore, from all points of view, the aircraft operation is deemed to be safe,
in accordance with ICAO and other related agencies regulations.
But as I said that the helicopter service will be maintained during and
potentially after construction. And
that the project itself is compatible with surrounding and adjacent land uses.
Proposals were afoot and I think are still anticipated for the
construction of a cricket pitch adjacent to the project.
It’s important that when we are planning and designing the facility
that this airport is fully compatible from all points of view in terms of line
level, accessibility, generally, compatibility with other land uses.
That the environmental impact is being fully explained, analyzed and the
proposals are in place for the mitigation of any adverse environmental impacts
and similarly social impact considerations, that being resettlement and other
disruption either during construction or as a result of the permanent works.
Not least, that the project itself comes in within budget.
A budget of $EC41 million is the prescribed budget for the work currently
envisaged. It is the design
team’s responsibility, absolutely, to ensure that that estimate is kept within
and that must include contingencies. That
must provide of course for all of the engineering findings that take place over
the next few weeks and that it is an absolute that that cost estimate not be
exceeded.
And that an effective dialogue is maintained between the team, Government
of Montserrat and the major stakeholders and the public. The major stakeholders in this project, of course, will
include not just the government but airlines, other operators, the community and
other users.
That there should be a benefit to the local economy from the project and
a transfer of skills during the project design and construction and that also as
I’ll mention later that there should be a maximization that the potential for
the use of local labor and materials on the project itself.
Now the program, as I said, is extremely tight.
I must say that when we first saw this program, it was something of a
shock to us. Although the project
itself is not rocket science, it is nonetheless an important and strategic
facility. As I’ve mentioned, it
must comply with international standards and it’s very tight.
The advantage is that a lot of good work has been done up until this
point. There is nothing in the work
that we’ve seen to raise major concerns or doubts over the recommendations
made. We feel we are starting on a
good foundation and that was advantageous to us in our response to DFID that we
could achieve this program. Otherwise,
I think starting from scratch that would have been an extremely optimistic call.
The first phase of the project is effectively planning and design.
Right at the front, a planning phase or a scoping phase.
To begin with, investigations, firstly geotechnical investigations, which
are now being completed, samples are currently being analyzed.
I’ll talk later about some of the investigations that we’re
undertaking on meteorological aspects including wind and turbulence; studies
which will confirm the runway length requirement for the operating parameters
that we are looking at for the Twin Otter; and the normal planning studies that
would take place for a project of this type, which is the specification,
effectively, of the geometry of the airport, the location of the building and
the separation of the various elements and the other parts of the infrastructure
for the project.
Now, the first phase of that project having then reached its inception
stage, would be completed within four months—from weeks 1-17 to complete at
the end of May 2002. We have
something like 10 weeks to complete the planning stage, which will basically
nail down the project in terms of runway length, location, alignment and then a
period of just 6 or 7 weeks to actually finalize the detailed design and
specification.
So by the end of May, we will have completed Phase 1a, the detailed
design. One and a half months or
six weeks are allowed for the tender process.
We would be expecting to be following international procurement
regulations on this—or practices—on this project, which is effectively an
open tender.
And we would expect to find ourselves by July 2002 in a position to be
able to actually award the contract. Mobilization
of the contract would start in August 2002
(Break in tape)
… specified in the tender documentation for completion in December
2003. Total duration of the
project: 21 months.
Now running through those points in a little more detail:
The investigations and studies—we’re here actually on a
familiarization process but it is an intensive working visit.
Work has already started on the geotechnical work, as I’ve said, not
just geotechnical mapping but topographical mapping is being refined.
The topographical survey using a digital ground modeling essentially for
the optimization of the major earthworks on this contract is quite a critical
part of this early process.
The runway length requirements will be determined through performance
studies, through operators and through experts in organizations such as the
Civil Aviation Authority who’ll confirm our own studies on what the
requirements are for runway length on a given set of sectors.
Assumptions have to be made on what the likely sectors and destinations
from Montserrat would be—principally, Antigua, of course, but other sectors
may be examined.
And so the purpose of the operations and performance study is to
determine exactly what the runway length requirements are at Geralds for a set
of operating conditions, payloads and sector lengths.
The climatological study is something which is about to take place.
There has been talk I know of concern over turbulence.
There are two aspects to this: Firstly,
crosswind. All airport planning
studies have to determine a crosswind component to enable the operator to be
assured of a good utilization. At
large airports where there are more than—there’s a possibility of having
more than one runway, crosswind is not a problem.
On small airports, where only one runway is viable, the rules and
regulations state that aircraft must be able to operate into that airstrip for
no less than 95%, in this case, of the time.
Over three years of wind records currently are available and many more
years of wind data through Antigua and Blackburne demonstrate over 98%
utilization, which gives us a lot of confidence in utilization.
However, further work has to be done in order to demonstrate that
turbulence on the approach—particularly on the approach from the west,
obviously, is not a problem. And
what we are doing there is undertaking a modeling process, which is effectively
a physical modeling process which will simulate a whole range of conditions
using a visual technique—using smoke traces but also a mathematical output to
enable us to present to the licensing authorities such evidence as they will
need to enable them to be confident that the operation is safe or that the
conditions which give rise to turbulence can be anticipated and notified to
operators in order to completely reduce those risks to acceptable levels.
And environmental scoping study, which will start in three weeks
time—our expert visiting would examine the key issues and plan the mitigation
measures.
Into the inception design, the preliminary studies I’ve just described
will enable us to start with confidence on the basis of the design which is
effectively the airport master plan layout that would determine effectively, the
classification of the airport, line level, runway length, so on and so forth.
So we’re building on those studies which we’ve undertaken in the
first few weeks of this project to give us confidence in the final adopted
design.
To begin with there’s a need to assess the suitability of what’s
already there at Geralds. The
terminal and the tower are the two obvious examples.
Some work will have to be done to determine whether or not they can stay
where they are. They are
not—certainly the building is not particularly portable but the construction
of a new building is not going to be cheap and so that is a factor and a
balancing act that will have to take place to determine whether the building can
stay where it is in the context of the runway location or whether it will have
to be moved and reconstructed. It
is quite likely that whatever solution is adopted that the air traffic control
tower will have to be moved.
There are other areas of infrastructure including the existing road,
which will clearly have to be diverted and we are looking again for the optimum
solution on the diversion of that road, whether it be to the east or to the west
of the runway is yet to be determined.
This approval process will lead to planning application.
During this process, discussions will have to be held with the two
funding authorities on what the procurement strategy will be.
The procurement strategy being the process by which the works are
tendered and awarded. Different
funding authorities have different sets of rules and regulations; some are more
pedantic than others. On the other
hand, those that, shall we say, are less intensive and provide more freedom
sometimes also give problems to us. So
clarity will be sought on exactly what is the preferred procurement strategy for
this project will be and how the different components of the project may be
packaged and let either in one contract package, or in two or several.
That procurement strategy will also, of course, have to address the issue
of the requirement for contractors to pay attention to maximization of local
expertise in terms of construction and other skills.
During this process, it is highly likely that there will be a
pre-qualification phase in which international and regional contractors will be
asked to file their expressions of interest for parts or all of the components
of this project. And those will be
evaluated in line with the funders’ requirements in order for the short list
of contractors can be submitted for approval to the Government of Montserrat.
Cost estimates, of course, have to be built up throughout this design
process. We certainly want to
identify any early warnings of overruns. We’ve
already started doing that with the geotechnical investigations but it’s
obviously vital that the Government is made aware of any fatal flaws in any of
the assumptions made already, which might bring rise, give rise to major cost
escalations.
Phase 1a continues with the preparation of a full environmental impact
assessment and the addressing mitigation measures before we go into the detailed
design process.
Now the detailed design process is what we, as a team, have all been
trained for the last 20 odd years to effectively pour all of our attentions
into. The planning phase is
essential. It is there that things
can go extremely wrong if that’s not bolted down properly but the skills of
engineers in terms of designing airport terminals, pavements and special systems
are brought into full effect during the detailed design process.
And that design process will specify exactly the materials used,
precisely, the geometric alignment of the facility—the runway, taxiway and
apron, arrangements for services—utilities, power supply, the diversion of the
road, security fencing, lighting and the many other associated aspects of the
project.
Design and building approvals need to be sought through Government
departments before the tender and tender evaluation process.
As I’ve mentioned, pre-qualified firms, if this is the procurement
strategy that we follow—it is not uncommon for a project of this size could
attract pre-qualifications if it was let as one—from 20, 25 companies.
It would be impractical to invite 20 or 25 companies to bid for a project
like this. In our view, it would
and it is quite likely that we would expect something like 6 companies to be
tendering for a project of this size. So we’d be inviting tenders from firms which meet all of
the pre-qualification criteria for a job of this type, whether it be let in one
package or several.
During that process, contractors are encouraged to—and will obviously
have a great desire to visit the site, inspect it, determine what the risks are
in pricing that tender, asking the consultant and the Government of Montserrat
whatever questions they may have on some areas of the works that are perhaps not
too clearly explained in tender documentation, so clarifications are required.
The whole process is one by which what is being aimed at is the
securement of good tenders which haven taken on board all the risks and are
tenders from companies which we can be confident would deliver an excellent
finished product. Obviously, one is
also looking for tenders from companies that are not inclined to submit low
tenders in order to win the job and then make excessive claims having being
appointed. And this is the process
by which tenders are evaluated when received, negotiated and awarded.
Recommendation would then be made to the funders for the award of the
contract or contracts. Following
the award, contract documentation is finalized and as I’ve said, we expect
that by July or August we would be in a position to actually award this contract
for start on site in August 2002.
The consultant does— moving towards the conclusion of my
presentation—Consultants responsibilities don’t end with the completion of
the design and the negotiation and award of the contract.
During the entire construction period, Halcrow would have a
representative, a resident engineer, assistant resident engineer, certification
engineer present on site in order to make sure that the contractor is working in
accordance with the specification and contract documentation.
One of the contractor’s responsibilities is to follow the environmental
mitigation plan. Resident
engineer’s responsibility is to approve the contractor’s working methods and
program; to implement, supervise and certify the work; submit regular progress
reports to the funders, the Government; ensure that the EMP is fully implemented
and of course as we are here to do today, to keep the public informed through
periodic meetings as to exactly what’s going on on-site, whether we are ahead
of, behind, progress on budgets and what other concerns the public and the
contractor and other agencies may have about the project.
And ultimately to submit a maintenance and final project report before
the process of final certification.
Once the process is physically complete, flight-testing is undertaken.
That testing is—would be undertaken under the auspices of the DCA and
the Government of Montserrat itself. The
flight-testing process helps us to calibrate the equipment that’s been
installed on the airport and to, of course, absolutely confirm that the
operation is safe and compliant with international requirements before the
license is applied for and received.
Now that’s a—as I said, perhaps a rather dry description of this
planning and design process. It’s
something we do every day. It’s
something we’ve done at a number of airports of similar sizes throughout the
world. We’re very familiar with
the territory and what the challenges are.
But I do say that this is quite a unique situation for us given the
circumstances in Montserrat and, of course, the desire for Montserratians here
to travel to and from the island and of course, Montserratians abroad to access
the island, perhaps to return to the island permanently.
So, in summary, this is where we—what we are about: early identification of what the priority issues are.
As I’ve said, we’ve already moved in that direction with the
geotechnical work; that we believe to be a priority issue; what the key
stakeholder requirements are and the commercial imperatives.
Delivering within time and on budget is an absolute.
This has been made very clear to us in our terms of reference.
There is no contingency over and above the budget specified and it is our
job to make sure that this project comes in on budget.
Otherwise, we might be in a St. Helena situation and get nothing.
Efficient coordination of all design and study components is a natural
part of the process for the study team. Coordination
with the Government of Montserrat, the Antiguan DCA, agencies to whom the DCA
consult, of course, which include the Federal Aviation Administration and the UK
Civil Aviation Authority, the EU and DFID, the two principal funders.
Ensuring that operating procedures are absolutely safe, certifiable,
compliant, have been tried and tested. As
I said at the beginning, there are some additional pressures on us following the
events of September and some sharpening up of the codes and recommendations in
that respect.
And last but not least, to address and to control the environmental
impact and the social impact brought about by this project.
So that is obviously a very, I would say, a very brief sketch of what we
are going to be doing between now and July this year in terms of design and
what, hopefully, should the project receive—which, obviously, we hope it
will—what our responsibilities will be until January 2004 in completing and
handing over the project.
So thank you very much for listening—for your patience in listening and
look forward to any questions you may have at the end of this session.
Thank you. (Applause)
C. Hogan:
Thank you very much Mr. Bill Millington.
And ladies and gentlemen, at this point, it is my pleasure to basically
invite you to engage us in an interactive segment.
And the forum will continue as follows.
You may ask questions of the panel and I’ll use my best judgment and
ask one of the most competent of the experts to answer your question.
We have five gentlemen in the significant areas that have been addressed
and many of them will be able to embellish further some of the points made by
Mr. Millington—which I found was quite informative and comprehensive.
So I’m basically opening the floor to you and you can ask your
questions from the center of the aisle there and we’ll take your questions
unless you are totally convinced. Or
you prefer for me to ask the first question?
R. Tyson:
Good evening. In your terms
of reference, you’re talking about a Twin Otter.
Could you tell me what length of runway is required for a Twin Otter to
comply to all the safety standards of an aborted flight if necessary?
B. Millington: It’s
a complex answer because it depends upon exactly what the operating parameters
are for the aircraft. And another complexity for those who followed the saga to
date is that suggestions have been made that the aircraft, the Twin Otter can
operate in either STOL or conventional mode.
Now, part of our work in the first 10 weeks is to rigorously scrutinize
the assumptions on operating parameters for the Twin Otter and other aircraft
types. First of all to iron out the
question of whether or not the aircraft is going to be permitted or whether
indeed, it’s even desirable for a Twin Otter to operate in STOL mode.
I will say that the Civil Aviation Authority in the U.K. are not overly
comfortable about STOL operations.
For those who perhaps are not aware STOL is Short-take-off and-landing,
which was a method of operation brought about in Canada some 25 years ago and
suited to a particular airport environment, suited also to a particular aircraft
type at the time, a Dash-7.
The short answer to your question is that a detailed analysis of the
runway length requirements for the Twin Otter in STOL and non-STOL mode is being
undertaken, also to a range of destinations and a range of…
R. Tyson:
You’re not answering my question.
The manual …
B. Millington: Well,
you asked me what the runway length requirement …
R. Tyson:
I asked you what distance is laid down in the manual that is required for
a Twin Otter …
B. Millington: The
runway length?
R. Tyson:
The runway length in STOL, the accelerated stop distance in an aborted
flight and if you can’t meet those requirements, will you still build an
airport?
B. Millington: Well,
if you mean an aborted takeoff, all runways are designed for an aborted takeoff.
That is one of the rules of the game.
We have to design a runway for what we call the accelerated stop
distance.
R. Tyson:
You design a runway to comply to the aircraft manual, surely.
B. Millington: Yes
and the aircraft manual …
R. Tyson:
And the aircraft manuals say, you need 695 meters …
B. Millington: At
maximum range in take off …
R. Tyson:
So you’ll be flying with half payload, half passengers?
B. Millington: No.
We’re flying to destinations or we would be but I don’t want to
pre-empt this analysis. We’re
looking at a range of payloads and range of, or certain range of situations and
a range of operating circumstances for that aircraft.
And as I said, the complication that the aircraft can operate in STOL or
conventional mode means that there is not one answer to the question of what the
accelerated stop distance for the Twin Otter is. There are at least four different answers for that question.
It very much depends upon exactly what the, shall we say, the route
structure that we’re offering is, whether we’re flying to Antigua, only to
Antigua, or whether we’re looking at St. Martin, whether we’re looking at
Guadeloupe, whether we’re looking at Nevis, which we obviously would, if we
were looking at Antigua. But what
we have to do is to look at a matrix of operating parameters in order to
determine what a safe runway length is for a …
R. Tyson:
If you can’t, if you could not get a 650 or 695 meters, which the
manual categorically states—and I’ve got it here with all the graphs and the
logs.
B. Millington: Yeah.
R. Tyson:
I am a pilot. I’m not a
commercial pilot. But the safety
aspect of this airport concerns everybody on Montserrat.
B. Millington: Yes.
R. Tyson:
If we’re going to spend, or you’re going to build an airport that
will not be certified and licensed for a 19-seater Otter, and we end up with a
9-seater at a temporary airport for the next five years …
B. Millington: I
think if we ended up with a 9-seater operation, we do not have a project.
That is a clear requirement of our terms of reference.
Our terms of reference require us to determine what the runway length
requirements would be for a Twin-Otter operating on a full passenger capacity,
whether it’s 17, 18, or 19.
R. Tyson:&n